It’s my second week at work and the site work is becoming easier and more understandable
On this day I spent my time in the office understanding how tenders are sent out to local contractors. Something to note is that the type of contract used was the JBCC and because the client is the university there is a rule the contractor has to follow which is employing local subcontractors


After drafting the tender a set date for submission is given. they other tenders go out, the other trades also come in so the selection of the lowest and most reasonable bidder.